District Project Details

SN Name of Project District Amount Sanctioned Date of Sanction Development Work Completion Date Expenditure Status of Project Decision Taken Image
1 For Purchase of Balers to achieve Zero Paddy Straw Burning in 10 villages Moga 300,000 01-08-2023 30-08-2023 275,000 o UC of Rs.266.05 lac sent to NITI Aayog.
o With this amount, 20 Balers have been purchased and given to Cooperative Societies of the District.
o To depute SDM or any XEN to check the availability of the balers.
o Further, its utilisation and outcome needs to be analysed.
o Data be provided wrt paddy straw residue baled out to nearby companies.
2 test Moga
3 Construction of 34 Incomplete Anganwadi Centre Buildings with provision of play materials Ferozepur 400,000 08-08-2023 24-08-2023 380,000 near to complete Construction of 34 Incomplete Anganwadi Centre Buildings with provision of play materials
4 Procurement of Equipment and Goods in District Hospital Ferozepur 850,000 10-08-2023 31-08-2023 750,000 in progress Procurement of Equipment and Goods in District Hospital
5 Smart Classroom Solution in 269 Schools Rupnagar 100,000 12-08-2023 31-08-2023 50,000 on going
6 Construction of 34 Incomplete Anganwadi Centre Buildings with provision of play materials Rupnagar 200,000 12-08-2023 30-08-2023 100,000 on going Construction of 34 Incomplete Anganwadi Centre Buildings
7 abs Rupnagar 10,000 11-08-2023 31-08-2023 200 on going ddddw